Construction progress – As of the date of this report the following tasks have been completed since the last update

Phase 1:  Complete

 

Phase 2:

Back ramp 80% complete

Front ramp 50% complete

Backfill and compaction 100% complete

All internal walls in basement and main level complete

Sewer and water service from street into building

All internal plumbing roughed in

Stairwells, landings,  and elevator pit to main floor complete

Second floor bar joists are installed

Second floor metal decking complete

Designated stained glass windows removed from Athens

Note

Although the Sanctuary and Chapel building will be ready for occupancy on October 1st, the Social hall building will not be ready to host any activities in the month of October. 

 