Construction progress – As of the date of this report the following phase-2 tasks have been completed since the last update

· East Ramp complete except gutters & downspouts

· 8’ drywell installed in north parking lot, underground downspout diverters installed to drywell

· 4’ drywell installed on south side of building and underground downspout diverters installed to drywell

· Parking lot filled with modified base and graded

· Concrete poured on front ramp – 60% complete

· Second floor decking complete

· Rafters for roof complete

· Roof sheeting complete

· Roofing 20% complete

· Gable ends studded and sheeted

· Concrete pad for A/C condensers poured on North side of building

· Kitchen cabinets ordered

· Kitchen equipment ordered

· Rough in electrical work 80% complete

· Rough-in plumbing work 80% complete

 