Construction update 3/20/2018
Construction progress – As of the date of this report the following tasks have been completed since the last update
- 3rd level future bathrooms framed, door openings framed wall outside bathrooms finished
- Stainless countertops in kitchen finished
- Outside doors near kitchen and northwest stairwell installed
- New hot water baseboard heat run to 3rd level annex complete
- New subfloor installed in social hall
- Rainbow colored accent walls painted in basement class rooms
- Basement floor painted
- Gas lines fully installed and operational
- Two furnaces installed and tested
- Siding on north side complete (east side still remaining)
- Baseboard and door molding painted and ready to install.
- Gutters and downspouts installed
- Granite sills installed in basement and main level
- East door (facing manse) installed
- Bathroom floors tiled