Construction update 11/27/17

Construction progress – As of the date of this report the following Phase 2 tasks have been completed since the last update:

· Roof 100% complete

· Fascia and soffits complete

· Stairwell towers and elevator framing complete

· Kitchen floor complete with poured epoxy

· Rough-in electrical complete

· Rough-in network cabling complete

· Rough-in plumbing complete

· All interior framing complete, ready for sheetrock

· Heating systems and ductwork 50% complete

· Roof sheeting complete

· Windows received, installation 20% complete

· Sheetrock subcontractor engaged, starting early December

· Spray foam insulation in attic scheduled for early December

 